2025 Women Build Project Schedule
2025 Women Build Project Schedule
|
Date |
Build Week # |
Work Activity |
|
|
|
|
|
Mar 26 |
Site/Tools Safety + Framing I Clinic |
|
|
Apr 05 |
Site/Tools Safety + Framing II Clinic |
|
|
Apr 12 |
Sheathing Exterior Walls Clinic |
|
|
May 30 |
Build Shed (experienced vols only) |
|
|
May 31 |
Build Shed (experienced vols only) |
|
|
Jun 6 |
0 |
Build Headers, Wall layout |
|
Jun 7 |
0 |
Build Headers, Begin framing |
|
Jun 13 |
1 |
Frame Walls |
|
Jun 14 |
1 |
Frame Walls, Frame Windows |
|
Jun 20 |
2 |
Sheathing, Wrap, Scaffolding |
|
Jun 21 |
2 |
Install Trusses, Bracing |
|
Jun 27 |
Sheathing, Wrap |
|
|
Jun 28 |
Sheathing, scaffolding, roof framing |
|
|
JULY 4th W/E – NO WORK |
||
|
Jul 11 |
3 |
Install Roof Decking |
|
Jul 12 |
3 |
Install Felt, Sheath & Wrap Gables |
|
Jul 18 |
4 |
Windows/Doors, Rat Runs, Attic Floor |
|
Jul 19 |
4 |
Blocking, Bracing, Clips, Site Cleanup |
|
JULY 25-26 – CANCELLED |
||
|
Aug 1 |
5 |
Shingle |
|
Aug 2 |
5 |
Shingle |
|
Aug 8 |
6 |
Vinyl Siding |
|
Aug 9 |
6 |
Vinyl Siding |
|
Aug 15 |
7 |
Vinyl Siding, Prime/Paint Walls |
|
Aug 16 |
7 |
Vinyl Siding, Prime/Paint Walls |
|
Aug 22 |
8 |
Vinyl Siding, Interior Trim, Paint |
|
Aug 23 |
8 |
Vinyl Siding, Interior Trim, Paint |
|
LABOR DAY W/E – NO WORK |
||
|
Sep 5 |
9 |
Siding, Paint, Trim |
|
Sep 6 |
9 |
Siding, Paint, Trim |
|
Sep 12 |
10 |
Paint, Trim |
|
Sep 13 |
10 |
Paint, Trim |
|
Sep 19 |
11 |
Paint |
|
Sep 20 |
11 |
Paint |
|
Sep 26 |
12 |
Paint/Shelves |
|
Sep 27 |
12 |
Paint/Shelves |
|
Oct 3 |
13 |
Paint/Towel Bars/door knobs |
|
Oct 4 |
13 |
Paint/Towel Bars/door knobs |
|
Oct 10 |
14 |
Storm Door, Punch list/Touch-ups |
|
Oct 11 |
14 |
Storm Door, Punch list/Touch-ups |
|
TBD |
15 |
Landscape/Punch List |
|
TBD |
15 |
Landscape/Punch List |
|
TBD |
16 |
Final touch-ups (final inspection) |
|
TBD |
16 |
Final touch-ups/ Clean out shed |
|
TBD |
|
DEDICATION |